Margaret Street sinkhole fill works begin

Margaret Street sinkhole fill works begin
18 January 2024

Filling the Margaret Street Sinkhole

The first step was to excavate the loose material from the base and sides of the sinkhole.
Excavation at sinkhole
The first step was to excavate the loose material from the base and sides of the sinkhole.
Heavy machinery was then used to drill two 600mm holes at the location of the known cavity extent found during the geological investigation.
Machinery 1
Heavy machinery was then used to drill two 600mm holes at the location of the known cavity extent found during the geological investigation.
Machinery
Drilled holes
Three cubic metres of concrete was used to fill the two holes.
Filled holes
Three cubic metres of concrete was used to fill the two holes.
Margaret Street Sinkhole Drone
A stabilised sand mix was pumped into the sinkhole cavity.
Stabilised sand mix in cavity
A stabilised sand mix was pumped into the sinkhole cavity.

City of Mount Gambier is working with a local concreter to fill the sinkhole in the walkway between Margaret Street and the Railway Lands.

The cavity first appeared when the bitumen collapsed following heavy rain in June 2023. Since then, an independent geotechnical investigation has been undertaken by engineering consultants, providing recommendations to fill the void that has a footprint of about 30 square metres.

“Due diligence on this solution has taken some time. Following independent advice, we are filling the cavity with stabilised sand, a mixture of soil and four to six per cent concrete,” City of Mount Gambier City Infrastructure General Manager Barbara Cernovskis said.

Site access in the vicinity of the sinkhole on Margaret Street is limited and a traffic management plan is in place during the drilling and filling process.

“We had heavy machinery on site on Wednesday 17 January 2024 to drill down to the void at two locations. The void was identified using a camera and a torch lowered down on a rope. We have now filled the augured holes with concrete which is an extra wet mix so it flowed into the voids in the underground cavity.”

“Today we built up the base of the sinkhole with 30 cubic metres of stabilised sand to 2.5 metres below ground level. The filled material will now be left to set. Next week we will continue to add 90 cubic metres of engineered fill, similar to road fill material and then reseal the top so the walkway surface is reinstated.”

We are confident that once works to stablilise the site are complete, it will be safe to return the thoroughfare to the community. - City of Mount Gambier City Infrastructure General Manager Barbara Cernovskis

Walkway access to the Railway Lands will be reviewed once the work is complete.

“Depending on how things settle, we plan on reopening the throughfare in the next week or so.”

Council continues to work with adjoining property owners to ensure safety within the vicinity of the impacted area.

“We will install a crack monitoring system on the wall of the neighbouring business to monitor any further ground movement or settlement during the next 12 months,” Ms Cernovskis said.

Total remediation work costs for the project are sitting at approximately $160,000.

Media contact: City of Mount Gambier Media and Communications Coordinator Sharny McLean on 0413 798 327 or smclean@mountgambier.sa.gov.au